Electrical Power Outage Notice for Smith Center North Tower - Massachusetts Avenue Side (3/14)

Scheduled Maintenance Report for HUIT

Completed

The scheduled maintenance has been completed.
Posted Mar 15, 2025 - 04:00 EDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 14, 2025 - 20:00 EDT

Scheduled

From Friday, March 14, 2025, at 10:00PM to Saturday, March 15, 2025, at 6:00AM, there will be no normal electrical power to Smith Center North Tower - Massachusetts Avenue Side.

The purpose of this scheduled electrical outage is for a contractor to test emergency lighting systems at Smith Center North Tower - Massachusetts Avenue Side.
Posted Mar 13, 2025 - 15:15 EDT
This scheduled maintenance affected: Utilities (Electricity).